JXSC has provided a successful 20TPH rock gold ore processing plant in Mozambique. We design the ore process plant flowchart & plant layout drawing according to ore conditions and offer a complete set of plant machines.

Introduction

Minerals: Rock Gold
Capacity: 20 TPH
Feeding Size:  <340 mm
Process: Feeding -> Crushing -> Gravity separation

Solutions & Process

Rock Gold Ore Processing Plant

This setup is a rock gold process plant.

  • The plant is configured with a hopper connected to 1 electromagnetic vibrating feeder under the hopper to feed materials more evenly into the coarse jaw crusher.
  • The coarse jaw crusher crushes the big stone to less than 100mm, and the output is transported to the fine jaw crusher via a belt conveyor.
  • The first crushed materials go to the fine jaw crusher, which crushes them to less than 30 mm fineness.
  • Materials less than 30mm enter the transfer bin and then go to the hammer crushers, which are crushed to a 0-2 mm range.
  • The materials go to the gold centrifugal concentrator for the first separation.
  • Tailings of centrifugal concentrator go to sluice box for recovering more gold;
  • The centrifugal concentrator and sluice box concentrates are sent to the shaking table to concentrate gold.
  • The shaking table is a gravity equipment for recovering gold, with a very high recovery rate. It is very friendly to the environment.

Equipment Lists

  • Electromagnetic vibrating feeder
  • Jaw crusher
  • Hammer Crusher
  • Gold centrifugal concentrator
  • Sluice box
  • Belt conveyor
  • Shaking table
  • Gold furnace

Main Equipment Used in This Case

Other Cases

Scroll to Top